Works are progressing well at our Ratcliffe Cross Street project on behalf of Notting Hill Genesis.

At Site A, the reinforced concrete (RC) frame has now reached the 3rd floor and scaffolding work has  commenced on the external face of the new structure.

At Site B, the groundworks, drainage works and ground beam installation are complete and the concrete RC frame has commenced.

This development is due to complete in the summer of 2020.

Key updates

Site A

·        RC frame construction in progress

·        3rd floor slab has been poured

·        Currently constructing the columns to take the 4th floor slab

·        Externally the scaffolding works are underway

Site B

·        Groundworks & drainage complete

·        RC frame construction in progress

·        1st floor slab has been poured

·        Currently constructing the columns to take the 2nd floor slab

Find out more about Ratcliffe Cross Street