We are now out of the ground and making preparations to cast the ground floor slab of our new 25 unit development on behalf of Hackney Council.
The drainage and underground connections are complete and the tower crane has now been installed on site.
The ground beam installation is progressing well and on schedule. We will shortly start work on the reinforced concrete frame phase of the project.
This development is due to complete in the summer of 2020.
Key updates
- Tower crane installed
- Ground beams complete
- Ground floor slab is currently in progress
- Shortly commencing the reinforced concrete (RC) frame