Marius-Cornel Vasile is Project Manager at Ratcliffe Cross Street in 

At Block A Marius and his team have:

  • Completed the 1st fix electrical and mechanical
  • Carried out the pre-plaster inspections on the upper levels
  • Closed up the ceilings from Ground floor to level 5
  • Continued the plastering from the ground floor to level 5
  • Made progress on the carpentry for the doors, skirting and architrave from the ground to 1st floor
  • Worked on installing the kitchens to the ground and 1st Floor
  • Installed the flooring and completed it up to level 3
  • Commenced the 2nd fix for the Mechanical and Electrical
  • Completed the lifts installation
  • Completed the 1st fix mechanical and electrical in communal areas
  • Carried out the pre-plaster inspections

At Block B, the team have:

  • Completed the 1st fix electrical and mechanical
  • Carried out the pre-plaster inspections carried out
  • Been closing up the ceilings and plaster from 2nd Floor to 5th Floor
  • Commenced the installations of both lifts
  • Completed the 1st fix mechanical and electrical in communal areas
  • Carried out the pre-plaster inspections