We’re now laying the brickwork on the 2nd floor and finishing off brickwork up to the 3rd floor. We’re fitting out the flats on the ground and 1st floor. The show flat has been plastered and the  kitchen and bathroom fitted. Now we’re just waiting for the flooring and tiling to complete.

The 1st fix electrical has been completed up to the 2nd floor and the 1st fix plumbing is now fitted through the 1st floor. Now we’re starting work on the 4th floor walls.

Jake Manzi  is our Assistant Site Manager apprentice

Terry Forsyth is Gateman, Traffic Marshall and all-round hero

Dennis Callan is Site Manager

EA – Pellings

Client – Hackney

Matthew Carr – EA