We’re pleased to report that development is on schedule at our Frampton & Lyttelton project.
At Frampton, the piling works have been completed. The groundworks and pile testing is progressing well and we’re about to start work on the reinforced concrete frame works. At Lyttelton,the piling works have also been completed, the drainage and underground connections are progressing well and on schedule. The pile testing works are in progress and we’ll shortly start work on the reinforced concrete frame works phase of the project.
Key updates
Frampton
- Piling works complete
- Groundworks & pile testing – progressing well & to programme
- Shortly commencing RC Frame works
Lyttelton
- Piling works complete
- Drainage and underground connections – progressing well and to programme.
- Pile testing works in progress
- Shortly commencing the RC Frame works