Progress is happening fast at Frampton Arms

W Block:   

·         2nd to 3rd floor verticals commenced Friday 03.05.2019 – ongoing activity 50% complete 

·         2nd to 3rd floor balcony precast columns all installed Monday 07.05.2019

·         3rd floor decking commenced Tuesday 08.05.2019 – ongoing activity 30% complete

·         3rd floor precast balcony slabs installed Friday 10.05.2019

 C Block:  

·         2nd floor precast cantilevered balconies installed on Thursday 9.05.2019

·         Double height columns installation commenced Monday 13.05.2019

·         2nd floor rear precast balcony slabs on site and planned to be installed on week commencing 13.05.2019

·         2nd floor slab reinforcement due to commence after 2nd floor precast balconies have been installed

E Block:  

·         2nd – 3rd floor verticals 95% complete

·         2nd – 3rd floor precast columns installed Saturday 04.05.2019

·         3rd floor slab decking commenced Monday 06.05.2019, ongoing activity 30% complete

·         3rd floor precast balcony slabs installed on Friday 10.05.2019

The image below shows the progress line up to date on RC Frame.