Recovery project including redesign of façade to achieve compliance

Essex 2017

  • 8 storey social housing block accommodating 25flats
  • Guildmore appointed as recovery contractor following failure of previous two contractors
  • Identified and rectified compliance issues with façade design, including non-compliant insulation and lack of test data to verify performance of various materials.
  • Identified and rectified compliance issues with fitout design, including inadequate sizing of smoke extract and excessive travel distances.
  • Secured buy-in from BCO and NHBC to revised designs and completed works to achieve signoff