Lyttelton locals
We’re finishing up the concrete frame now and putting in the last pre-cast slab. The ground floor lifts are completed up to the 1st floor Read more …
Frampton – giving locals a fresh start
At Frampon Arms, the waterproofing work is in progress. We’ve laid the 1st layer of felt and the tanking should be finished this week. We’ve Read more …
Ratcliffe Cross Street – locals & apprentices
At Ratcliffe Cross Street, we’ve completed the external facade to Block A. Internally, we’re closing up the walls and ceiling on the ground and 1st Read more …
Lyttelton is growing up
A warm welcome to Dennis Callan – new Project Manager at Lyttelton. At our Lyttelton site, the steel frame structure (SFS) has started. We’ve installed Read more …
Arch success at Frampton
At Frampton, the 2nd arch has arrived and is being installed now. The last of the pre-cast Cornish concrete has been fitted and the mechanical Read more …
On top of the world at Ratcliffe Cross Street
Works are moving fast at Ratcliffe Cross Street. On Block A we’ve completed the window installation. We’ve 90% completed the external facade and this should Read more …