POPLAR BATHS RESIDENTIAL
- Parapet walls at roof level 100% completed.
- Stairs ground floor to 9th floor completed.
- Perimeter Metsec from ground floor to 8th floor completed.
- CP Board ground to 8th floor 75 % installed.
- Soil vent pipes from ground to 9thth floors completed.
- Plumbing first Ground floor 90% completed.
- Electrical first and 2nd floors 90% completed.
- Widows: ground floor 90% installed, first Floor 90% installed, 2nd floor 90% installed, 3rd floor 80% installed, 4th floor 15% installed
- Block work: Basement blockwork completed. Ground Floor 50% completed.
- External Envelope: East elevation- ground floor to 2nd floor completed.
West elevation-ground floor insulation 75% completed.
South elevation-insulation 50% completed.