FotorCreated

POPLAR BATHS RESIDENTIAL

  1. Parapet walls at roof level 100% completed.
  2. Stairs ground floor to 9th floor completed.
  3. Perimeter Metsec  from ground  floor to 8th floor completed.
  4. CP Board  ground to 8th floor 75 % installed.
  5. Soil vent pipes from ground to 9thth floors completed.
  6. Plumbing first Ground floor 90% completed.
  7. Electrical first and 2nd floors 90% completed.
  8. Widows: ground floor 90% installed, first Floor 90% installed, 2nd floor 90% installed, 3rd floor 80% installed, 4th floor 15% installed
  9. Block work: Basement blockwork completed. Ground Floor 50% completed.
  10. External Envelope:  East elevation- ground floor to 2nd floor completed.

 

West elevation-ground floor insulation 75% completed.

South elevation-insulation 50% completed.

Similar Posts

Leave a reply

required*