Scaffolding has now been taken down at Dame Colet Residential and finishing touches are being applied internally and externally, including the landscaped courtyard overlooking the St Dunstan’s churchyard.

Details are currently being finalised in preparation for the fitout of internal spaces at Haileybury, including a specialist training kitchen, sports hall and music room.
Brickwork has started at Poplar Baths Residential and the brackets are being fitted for the external finish which will be a defining feature of the building.
The pool tank for the new swimming pool at Poplar Baths Leisure is complete and about to be tested for watertightness. Steelwork is now being erected over this new pool while the interior of the pool hall in the old baths building is now filling up with scaffolding as works proceed to restore the interiors of this incredible space.