Brick removal
- North façade 100% completed
- West façade 100% completed
- South Façade 85% completed
Steel repair
- North façade 70% completed
- West facade 100% completed
Cementitious Coating
- North façade 70% completed
- West façade 100% completed
ICCP protection
- North façade 60% completed commenced 15.04.15
- West facade70% completed
Rebuild brickwork
West façade 50% completed
Concrete repairs
West façade 40% completed
Window removal
- North façade 95% completed
- West façade 80% completed
- South façade 80% completed
Class 1
Internal structural steel work 10% completed. Park steel to commence further steel erecting from 26/5/15
Demolition complete 90%
Class 2
Basement slab has been cast 50%
Drainage 50% completed
Muckway currently 70% off site