For more information, visit: http://www.poplarbathsanddamecolet.co.uk/news-2015/

Screen-Shot-2015-05-26-at-12.47.02

Brick removal

  1. North façade 100% completed
  2. West façade 100% completed
  3. South Façade 85% completed

Steel repair

  1. North façade 70% completed
  2. West facade 100% completed

Cementitious  Coating

  1. North façade 70% completed
  2. West façade 100% completed

ICCP protection 

  1. North façade 60%  completed commenced 15.04.15
  2. West facade70% completed

Rebuild brickwork

West façade 50% completed

Concrete repairs

West façade 40% completed

Window removal

  1. North façade 95% completed
  2. West façade 80% completed
  3. South façade 80% completed

Class 1 

Internal structural steel work 10% completed. Park steel to commence further steel erecting from 26/5/15

Demolition complete 90%

Class 2

Basement slab has been cast 50%

Drainage 50% completed

Muckway  currently 70% off site